Data Centers, Power · Private · Redwood City, US
SB Energy
US company that develops data-center campuses and the power plants that supply them.
- Largest stated capacity
- ≈8 GW
- 1 deal states this measure; they are not added
Funding
Financing events where SB Energy raised money or filed for it
| Date | Round | Equity | Debt | Post-money | Leads | Status |
|---|---|---|---|---|---|---|
| Aug 17, 2026 | Strategic investmentNVIDIA investment in total | $3B | Not tracked yet | Not tracked yet | No lead named in the source | Signed S-1 ↗ |
* Equity raised counts closed primary equity rounds only, per currency. It excludes debt, secondary sales, Form D amounts and money counted inside a later round. Other trackers often add some of these, so their totals differ. Method →
Investors named in primary sources
- Strategic
- NVIDIA
Amounts per investor are shown only when a source states them. Other named investors are listed on each round page.
Compute and infrastructure
Stated contract totals over multi-year terms, not annual spend
| Date | Deal | Role | Value (basis) | Capacity | Source |
|---|---|---|---|---|---|
| Aug 17, 2026 | OpenAI and SB Energy 20-year leases at the PORTS-Pike campuswith OpenAI, NVIDIA · Data-center lease, Warrant | Landlord | No dollar value stated in the source | ≈8 GW | S-1 ↗ |
Timeline
Every tracked event, newest first
- Aug 17, 2026InvestmentNVIDIA invests in SB EnergySB Energy$3BSigned S-1 ↗
- Aug 17, 2026LeaseOpenAI and SB Energy 20-year leases at the PORTS-Pike campusOpenAI ↔ SB Energy≈8 GWSigned S-1 ↗
Related
Sources
1 sources · reviewed Oct 21, 2026
- SEC EDGAR (SB Energy, Inc.), “SB Energy registration statement on Form S-1, filed September 1, 2026”, Aug 31, 2026 · S-1
Corrections: none. Found an error? Report it.